If you're a procurement person or operations coordinator tasked with sourcing a palletizer — layer, case, low level, high level, or conventional — this checklist is for you. I've done this a handful of times now, mostly coordinating between our plant manager, finance, and outside manufacturers, and the mistakes tend to repeat across buyers. Six steps, roughly in order. Total due diligence takes me about three weeks from first outreach to signed PO.

Step 1: Write Down Your Actual Throughput Before You Talk to Anyone

When I first started handling equipment purchases, I assumed vendors would help me figure out the right specs. Two months into one project, I realized the vendors were just mirroring whatever number I gave them — and I'd given them the wrong one. Now I ask our line supervisor for three numbers before anything else: cases per minute at peak, cases per minute at average, and how many SKUs the line runs in a typical week.

That last one matters more than people think. A conventional palletizer tuned for one product pattern struggles when you throw 40 SKUs at it (unfortunately, we learned this the hard way).

Checkpoint: You should be able to say, in one sentence, "We need to palletize X cases per minute, averaging Y, across Z product patterns." If you can't, stop here.

Step 2: Match the Palletizer Type to Your Floor, Not Your Wish List

This is the step most buyers skip, including me the first time. Here's the rough map I use now:

  • Low level palletizer — operator loads at floor level, good for lower throughput (think 10-20 cases/min), less ceiling height needed. Great for retrofits into older buildings.
  • High level palletizer — pallets build up high, best for higher throughput lines (30+ cases/min), needs real ceiling clearance and more floor planning.
  • Layer palletizer — builds a full layer at a time, then places it. Good fit for uniform case sizes and mid-to-high volume.
  • Case palletizer — handles individual cases, more flexible on mixed patterns, often slower per cycle.
  • Conventional palletizer — catch-all term; ask the vendor exactly what mechanism they mean before comparing quotes.

Before you get a single quote, walk the floor with a tape measure. Ceiling height, column spacing, distance from the end of the case conveyor to where the pallet needs to land. I've seen a beautiful quote get killed because the machine physically wouldn't fit under an existing sprinkler run.

Step 3: Talk to At Least Four Palletizer Manufacturers, Not Two

Two quotes tells you almost nothing. Three is better. Four is where you start seeing the market. In one round I ran last year, quotes for what looked like identical specs came in with a spread of about 35% — and the cheapest one was missing two items the others included as standard (safety guarding and a spare parts kit).

When you contact manufacturers, lead with your throughput numbers from Step 1 and your floor constraints from Step 2. Ask each of them the same three questions:

  1. What's the delivered lead time, and what's the actual install time on site?
  2. What's included in the base price vs. what's an add-on?
  3. Who services it within our region, and what's the typical response window?

Take the lead time answers with a grain of salt. I'm not 100% sure why some manufacturers consistently hit their quoted dates while others slip by weeks, but my best guess is it comes down to how much buffer they build into their own component sourcing.

Step 4: Normalize Every Quote Before You Compare

This is the step I'd put in bold if I could. Vendors quote differently. One includes installation, another doesn't. One bundles a training day, another charges for it. One quotes FOB factory, another delivered-to-dock.

Build a simple spreadsheet with the same line items across every vendor:

  • Machine base price
  • Installation and commissioning
  • Training (how many days, how many people)
  • Spare parts kit (initial)
  • Freight and rigging
  • Warranty length and what it actually covers
  • Service contract — included or separate?

Without this, you're comparing apples to palletizing robots. The first time I skipped it, I "saved" about $12,000 on the machine — and paid it back in add-ons within the first month (ugh).

Step 5: Ask About the Boring Stuff — Consumables, PLCs, and Spare Parts

Nobody likes this step. Do it anyway. Ask each manufacturer:

  • What PLC brand is used, and can our in-house techs access it, or do we need a service contract?
  • Which parts wear out fastest, and what's the replacement cost and lead time?
  • Is the HMI in a language our operators can read?
  • Are drawings and manuals provided at handover?

I knew I should ask about PLC access on one project, but thought "what are the odds we'd need to touch it in year one?" The odds caught up with me at month seven, when a sensor fault stopped the line for six hours because our techs couldn't log into the controller.

Step 6: Get the Acceptance Criteria in Writing Before You Sign

The contract should spell out what "working" means. Not just "palletizer installed" — but exact throughput at acceptance, test protocol, who supplies the test cases, and what happens if the machine underperforms on day one.

Include a retention amount (10% is common in my experience) tied to successful acceptance after 30 days of running. This one clause has saved me twice.

Things That Trip People Up

A short list of mistakes I've made or watched others make:

  • Underestimating compressed air and power needs. A layer palletizer can pull more air than the existing compressor handles. Check utilities before you commit.
  • Forgetting floor loading. Static and dynamic loads differ. If your floor slab wasn't engineered for this, you may need reinforcement.
  • Assuming "conventional" means the same thing to every vendor. It doesn't. Get the mechanism in writing.
  • Ignoring the operator handoff. A palletizer that only one person on your team can run is a single point of failure.

This checklist reflects how things looked in early 2026. Lead times, pricing, and safety standards in industrial automation shift quickly — verify current figures with each manufacturer before you budget. And if you've got a step I'm missing, I'd genuinely like to hear it. The sourcing process keeps teaching me things I didn't know I needed to ask.